TORONTO, ONTARIO--(Marketwired - March 1, 2016) - Duran Ventures Inc. (TSX VENTURE:DRV)(LMA:DRV) ("Duran" or the "Company") is pleased to provide a progress report on the construction of its 80% owned 100-tonne-per-day Aguila Norte mineral processing plant located in Northern Peru. The Company expects to finish construction of the plant by the end of March 2016. The commissioning phase would then start in early April with processing of third party mineral to commence shortly thereafter. The civil works were completed in late 2015 to provide the base for the primary crushers and for the 6' X 6' ball mill. The primary and conical mineral crushers as well as the ball mill were delivered to site...
↧